BACK TO WEB SITE

 

 


 

 

Testing and Analysis

Testing
- A ten part primer on testing by ATA president Barry Richard.

Part 1 - Introduction
Part2 - Understanding Requirements for a Forensic Test
Part3 - Planning the Test and Writing the Protocol
Part 4 - Selecting, Designing, Purchasing and Assembling the Test Hardware
Part 5 - Conducting the Test Meeting
Part 6 - Pre-Test Setup and Preperation
Part7 - Conducting the Test
Part 8 - The Post Test Process
Part 9 - Post-Test Disassembly and Cleanup
Part 10 - Post-Test Data Analysis and Reporting

 

 

 

 

 

Testing (Part 1)

By Barry Richard, CSP

If you have been in our facilities you know that ATA Associates does a significant amount of unique failure analysis testing to support our accident reconstruction activities. Additionally, our testing activities extend to product testing. We frequently receive requests to conduct tests to determine how a product failed, what caused it to fail, or whether or not the failure was caused by overloading that exceeded reasonable design parameters. Each time we are requested to provide an estimate of what it will cost to conduct the test.

However, it is reasonable for a client to ask for an estimate of the cost to conduct a test. Many times clients react in disbelief at finding what the estimated cost of a test will be. Generally it is because they do not fully understand what goes into planning and conducting a test. Many might think that it is simply a process of getting a few pieces and parts together and pushing them, pulling them or re-enacting the accident to see what they do. In fact, it may have actually been that simple in the past. Daubert has, however, changed the face of tests forever. Now it is imperative that experts conducting tests follow a methodology that has been documented and reviewed to assure accuracy, sufficiency and repeatability in the process. It is no longer sufficient to do the test, observe it and testify to it. The expert must be able to prove the results and provide raw data for the experts on the opposing side to review. For that reason, I think it will be of interest and benefit to undertake a series of discussions on what is involved in conducting a test.

Because of space limitations I intend to cover this topic in a series of articles. The first article will appear in our next issue. My purpose this time will be to outline the primary activities necessary to conduct a test and to set the stage for follow-on discussion.

I have broken the test process into 9 phases of activity that will provide subject matter for 9 issues. They are as follows:

- Understanding the requirements for the test.
- Planning the test and developing the protocol.
- Selecting, designing, purchasing and assembling test hardware.
- Conducting the pre-test meeting.
- Pretest set-up and preparation.
- Conducting the test.
- Post test data gathering.
- Post test disassembly and cleanup.
- Post test data analysis and reporting
.
Each phase may involve a small or significant amount of effort depending on the scope, data requirements and complexity of the individual test. Over the next few issues I will devote space to discussing elements of each test phase while addressing factors affecting the cost to the client in hopes of providing a little more understanding of the entire process.

BACK TO TOP

 

 

 

 

Testing (Part 2)
Understanding Requirements For a Forensic Test

By Barry Richard, CSP

The first step toward effective testing is to understand the reason for testing and what the test is supposed to achieve. This is usually done through discussions with the client and experts involved in the analysis of the event. It may not be possible to answer all of the questions at the first session, but a clear understanding of the issues and basics is a must before moving into the test planning and development process where capital resources become committed. This is necessarily a brief discussion of the elements, but the testing organization and all parties involved must begin with the following.

1. Understand the reason for the test – A major point to be made is that testing should not be conducted with the express purpose of proving or disproving a specific point. It should be conducted to understand performance elements within a defined set of parameters.

2. Understand the basis for the test - What was the failure scenario? Understand the sequence of events of the original failure as accurately as possible based on available information. This may initially come from the client, but must be verified through research into documents, statements of witnesses and photographs. Ultimately, you will have to explain your test plan and assumptions to a jury and you cannot say that you took the client’s word on everything. It may make you look as if your client manipulated you.

3. Understand the test parameters - Within what bounds is the test to be conducted? Some criteria must be established to make the tasks realistic. Naturally, you may not have the luxury of testing everything about a given system, so you test the things most clearly at fault. Questions that must be asked include: What components failed? What were the environmental conditions? What phase of operation was occurring? Were surface conditions a factor? What were the speeds? If there was an impact, what was the angle and speed?

4. Understand data requirements - What information do you hope to gain from the test? Ultimately, it is an understanding of how and why a failure occurred, but that answer may not be clearly discernable from the test. What may come from the test is a large amount of raw data and information that must be analyzed to get the final answer. So, what do you measure – temperature, pressure, speed, force, acceleration, strain, voltage, current, flow or some other parameters? Is normal or high-speed video needed? The decisions on what to measure and how, have a decided effect on the complexity of instrumentation and thus, the cost of the test.

5. Understand equipment and personnel requirements - Once the data requirements are understood, the equipment to gather the data can be defined. Additionally, test fixtures, locations and special equipment to handle the item(s) being tested can be defined. Finally, you can determine how many people will be required to conduct the test effectively.

6. Agree that the test is worth doing and commit to the necessary costs - You may not be able to get the cost down to the nickel at this point, but the client needs to be “prepared” for the realistic amount. It is better to overestimate the cost slightly than to let the client go away with an unrealistically low perception of the cost.

This is certainly not an all-inclusive discussion of the elements or time involved in this phase of the process, but it should give an understanding of the process. In our next segment we will explore the detailed planning for the test and development of the protocol document.

BACK TO TOP

 

 

 

 

Testing (Part 3)
Planning the Test and Writing the Protocol

By Barry Richard, CSP

Testing is frequently more complicated than the first look would make you think. As with any complicated operation, planning up front, discussing what is to be done, and putting it down on paper, can save a lot of stumbling and additional costs in making changes later on.
Important elements to this process:

1. Understand what the test is about – at least from a preliminary level, and make a list of all the people who need to be involved in the planning process.

2. Get the people together and have a meeting to talk about the test requirements.

Important items for discussion at the meeting:

1. What the objective of the test is.

2. What kind of data is expected from the test?

3. What equipment and support will be needed to support the test?

From that information, you can begin to formulate the sequence of events for the test, the location of the test, and how long the test would be expected to take. The meeting then becomes a brainstorming session with the group to organize and plan for all of the materials and equipment that will be required to support the test and make it successful.

As an integral part of the meeting, a rough outline of the protocol should be drafted. As the meeting develops, the protocol should come together as a natural part of the activities. You can discuss the flow of the test, the information to be acquired, and talk about details such as placement of sensors, measuring devices, cameras. The draft protocol then becomes part of the product of the meeting. It can be typed by the secretary or recorder, and then provided in draft form to the technical expert who will be responsible for reviewing the protocol, making any additions or changes to ensure the accuracy and correctness of the information and the processes contained in the protocol. At this point it becomes a final document. That needs to occur as quickly as possible in the early stages of the process because the protocol and its requirements ultimately drive the requirements for the testing location, the photography and number of cameras required, the instrumentation required, the data logging and equipment required, and the time required for the test, as well as determining the number of people that will be required to support the test.

This stage of the test process is often delayed until a few days before the test, or is relegated to a single individual with total responsibility for writing the protocol and determining what is to be done. That is, in fact, the least effective, least efficient, and most costly way, generally, to go about doing testing of any measurable complexity. For a small, single-item test that requires only minimal video coverage and manual measurement with standard measuring tools (such as rulers, micrometers, or a basic scale), that process will work. But, for any test requiring electronic data logging, coordination between more than two people, and acquisition of equipment and materials, it is imperative, from a cost and effectiveness standpoint, to have the meeting and write the protocol (at least the draft) very early in the process. Whether it is testing, or research and development, testing for operational proof, testing for litigation to prove hypotheses or to gather information for other purposes, the planning phase is where the final cost of the test is determined. Not only should the experts and the technicians who are being involved in the test be there, but also the client, who is driving and, ultimately, paying for the test.

Many people think of testing as something very simple that you just put together and go out and do in a couple of days. And, in fact, that can be done. It has been proven over and over again. What is also true, and has been proven over and over again, is that except for the simplest of tests, few people ever remember or think of everything that is required, nor get all of the data that could have been gotten, when they run their test in that manner.

The next issue will address the preparation and assembly of the equipment for the testing and cover implementation issues in preparation for the test.

BACK TO TOP

 

 


 

Testing (Part 4)
Selecting, Designing, Purchasing and Assembling the Test Hardware

By Barry Richard, CSP

Once the planning phase and the preparation of the test protocol are complete, the hands-on work of assembling the test begins. The steps of preparation include:

1. Selecting the components, parts, and support equipment to be used in the test. This can be a simple two or three items, such as a camera, a short stretch of road or parking lot, a decelerometer, and a pad of paper, with a vehicle and an operator; or it can be much more complex, including multiple vehicles, several cameras for documentation from different angles, sensors, and recording devices for temperature, pressure, speed, distance, acceleration, and other factors.

2. Once the equipment and components are selected specifically for their usefulness to the particular test, those that are not on the shelf must be ordered. Some items have lead times of as much as two to eight weeks for delivery, and that must be considered when thinking about planning for the test. It doesn’t do a lot of good to plan a test for a week from now, when a vendor cannot deliver a part for two weeks. Frequently, the task of finding certain components that are required for a particular test can be a research project of several hours, especially when specific operating parameters and cost are factors.
Purchasing the test articles and hardware (nuts, bolts, metal, cars, trailers, etc.) requires money, and that money must, generally, come from a client, unless the testing organization has the resources to purchase that hardware up-front. Once the hardware and all of it components are received, the task of assembling them in the proper manner, and assuring that they function properly every time, becomes the focus of the task.

Many times, especially for complex tests, the instrumentation of a vehicle or component can take several days of assembly, positioning, fastening, running wires, and securing equipment so that it does not become a projectile or get damaged in the event of a failure or loss of control during a test sequence.

BACK TO TOP

 

 

 

Testing (Part 5)
Conducting the Pre-Test Meeting

By Barry Richard, CSP

Meetings, meetings, meetings. None of us really like them. They take away time from doing the really important (or fun) things, but they are very necessary to the efficiency of conducting complex operations — especially when there is a large group of people involved. When testing is involved, a pre-test meeting is an extremely effective way to assure that everything is ready to go for the test. It is the last check, the last discussion session, the last chance at assuring that everything has been taken into account and will be there for the test -- from complex equipment, vehicles and people, all the way down to box lunches and enough water to keep folks from getting sick on a hot day.

Attendance at the pre-test meeting should be mandatory, either in person or by telephone, for the test lead or director, each and every one of the test participants, the client, and any other individuals who may be participants or interested in the test, its conduct, and its outcome.

This pre-test meeting is the last opportunity, in most cases, for someone to say, “I was thinking last night that I would also like to have this particular device or information.” What does everyone think?” It also is an opportunity for people to bring up their thoughts on the process or procedure, and to understand the sequence of events and timing of what will happen on the test date.

Things that should be specifically done at the pre-test meeting:

1. A list of all participants should be finalized.

2. The test protocol should be reviewed in detail from start to finish.

3. A list of responsibilities for each person – what they are to do, what they are to bring, and when they are to arrive at the test site – should be prepared.

4. And finally, a discussion of safety issues for the day of the test must be conducted.

This is an extremely important meeting to ensure that everything is where it is supposed to be, when it is supposed to be there, so that the test can proceed on time, efficiently, in a cost-effective manner.
Remember, time wasted, in many cases, is money wasted for the client when you have a team of five or six people at anywhere from $50 to $250 an hour, standing around waiting because you forgot to get some particular piece of equipment that is considered vital to the test.

BACK TO TOP

 

 

 

Testing (Part 6)
Pre-Test Setup and Preparation

By Barry Richard, CSP

The day of a test, or possibly starting the night before a test, organization becomes a critical element in the success and smooth running of any test process. Team members should have designated responsibilities to check and prepare all equipment and supplies, and package them, if necessary, for transport to the test site. Naturally, if a test is being conducted in your facility or in a close area where transport of items is not required, then it becomes a much easier task. However, there is still a task to be performed if the test is going to run smoothly when the observers arrive.
Equipment should be positioned, warmed up, checked-out, and tested beforehand to assure that it is working properly and that there are no malfunctions. This assures that when the test manager says, “Let’s go do the test,” that it can start at that time and proceed smoothly and effectively to a final conclusion. The preparation process is important in that if it is not done, and outside observers are coming to watch the test or to videotape it, your failures are captured forever and become a “sore thumb,” so to speak, in the documentation of the test that shows your lack of preparation.

Pre-test preparation and checkout is not practice for the test. It is assurance that the test will run smoothly and that you will have the highest assurance of obtaining the data the client and his experts need to make an accurate evaluation.

 

BACK TO TOP

 

 

 

Testing (Part 7)
Conducting theTest

By Barry Richard, CSP

The day of testing is the proof of whether or not your planning, preparation and expertise (skill and cunning) are adequate for the task. Keep in mind that total success is not a guaranteed commodity but good pre-test preparation and planning go a long way to stave off total failure. Anyone who believes that failure can’t happen to them is either very well prepared or very naive.

Start the day of the test prepared for hard work and long hours if the test is even moderately complex. The lead test engineer and the logistics support lead should begin the day before the test by inventorying all required supplies and equipment, assuring that all batteries are charged and spares are available and assuring that all persons involved in the test are prepared.

Be at the testing location early to re-check everything. This is relatively easy if your test is occurring in a controlled lab environment but gets more demanding if you are testing at a remote site. The bottom line is that you should start early enough to be completely ready to test before your audience arrives. All of your planning and preparation should be transparent to them.

Data collection equipment should be installed or positioned. This includes multiple video positions, 35mm photography, sensors and observer positions. NEVER depend on a single, non-redundant data collection method unless you have the luxury of running the test multiple times. If it is a one-shot test, the cost of added data collection and documentation capability is always justified.

Once at the test site, there should be one person designated as being in charge and having the final authority over the test conduct and safety issues. Everyone should have a job to do and should be constantly busy doing it.

Some specific tips concerning the test process follow.

- Number each test segment for identification. Make markers or signs that clearly identify each segment and record the segment number at every video position so that the videotapes can be matched.

- Use a flag or flash to put a start-run marker on the video for each segment so that the tapes can be time coded and coordinated if required.
- Put as many timing and distance markers as reasonably possible in the area of the test. They may be invaluable later if your electronic data logging equipment goes south on you. This author has seen more than once where manual analysis tools allowed usable data to be extracted from video cameras when the fancy stuff failed. Remember, even partial success is better than no success at all.

- Download data after the first segment and check it to assure that the equipment is working properly. After that, download after every four or five segments and save recorded data to disk in case there is logging equipment failure or damage.

- Have all film and video turned in to a single point for processing. Everyone who needs it should get copies but the master set should be in one location.

- Treat test articles as evidence if litigation is involved. Until determined otherwise by the litigating attorneys, the data and damaged articles are exactly that, evidence.

Note from the author: This is a necessarily brief overview due to space limitations. More detailed information can be found in SAE and ASTM guidelines and texts on the subject. I will endeavor to provide a detailed list of references as a final article for this series.

BACK TO TOP

 

 

 

Testing (Part 8)
The Post Test Process

By Barry Richard, CSP

It seems to be a generally recognized requirement that test conductors gather data during the test. After all, that is why we test. Still, a lot of data and information is lost during the test due to lack of preparation and attention to detail. Interestingly, it is not so frequently recognized that there is also significant amounts of data that are lost after the test is “over”. The reason for this is that many testers end the “test” phase too early.

After the crash . . . after the bang . . . after the crunch, everyone's desire is to move in and look, touch, and inspect. Too much haste and too little control of the test site can lead to parts being moved too soon, before they are properly documented. Post-test configuration, instrument and sensor condition, parts location and overall orientation and relationship of items should be documented by a minimum advance team first, before the crowd is unleashed to get their looks and pictures. The closer to the point of impact, prime failure area, or primary test component, the stricter the control should be until the primary investigator says he/she is finished and the area is released.

The post-test process includes photography, video, reading mechanical sensors and measures, retrieving data loggers, and assuring that all critical measurements are completed before anything is moved.

BACK TO TOP

 

 

 

 

 

Testing (Part 9)
Post-test Disassembly and Clean-up

By Barry Richard, CSP

“The Job Is Not Finished Until The Work Area Is Cleaned Up!!!!” Ever heard it? From dad to bosses it is a necessity that the test area is cleaned up. Quite often there are complex test jigs or course layout markings. There may be ground securements, signs, cups, snack wrappers, wires, marker cones, tables, chairs, or debris of some other sort. It should be cleaned up to leave the site in as near the same condition as it was when the test team arrived. This is not only environmentally necessary but it creates good will with the owners of the test site. No one likes cleaning up after guests.

In addition, inspection of the test apparatus and jigs during the disassembly process may reveal information about the loads encountered in the test.

BACK TO TOP

 

 

 

 

Testing (Part 10)
Post-test Data Analysis and Reporting

By Barry Richard, CSP

You have spent $50,000 dollars conducting a test. It is of absolutely no good unless the meaning of the data is revealed and documented for others to see and understand. This may take as little as 3 or 4 hours for a simple test where data recording was done manually and by video. On the other end of the spectrum when high-rate electronic data logging of multiple sensors is involved, the analysis process may take 40 to 100 hours of intense effort. This is a point frequently overlooked when attorneys or other clients request elaborate data sensing and recording technology. I am not discouraging the use of more sophisticated data collection techniques, they are often necessary and yield much more accurate data. The point is that all involved parties must realize the time and effort required to bring the data to a point where it is useful for writing a report. This is the time when the pre-test discussion of what and how to gather data pays off. Good planning up front means that you do not have to decide what to use and what to disregard in the analysis phase.

If the planning was good and the analysis only has to address pertinent data then the reporting of the results becomes significantly easier.

Once the final report is filed with all of the data attached;

THEN THE TEST IS OVER!

BACK TO TOP

 

 

 

 



 

 

 

 

 

 

 

 


BACK TO TOP

 


BACK TO TOP